Stadtwerke München Acquires a Majority Stake in the Holzheim Wind Farm
The involvement of municipal utilities, local governments, and citizen cooperatives is intended to strengthen regional economic growth and advance the expansion of wind energy in Bavaria.
November 12, 2026
Source: E & M powernews
GP Joule has found buyers for the wind farm currently under construction in the Bavarian town of Holzheim. Stadtwerke München, the municipality, and a citizens’ cooperative are purchasing the power.
Preparations are currently underway in the Weisinger Forest for the construction of a new wind farm. The four planned Enercon E-175 turbines in the Bavarian municipality of Holzheim are scheduled to begin generating electricity in the first quarter of 2028.
They will do so on behalf of an operator consortium to which the North Frisian project developer GP Joule is selling the four turbines. The company, based in Reußenköge, Schleswig-Holstein, has now announced that an agreement has been reached on a corresponding acquisition contract. No details are available regarding the investment volume.
According to the agreement, Stadtwerke München will acquire 74 percent of the Holzheim wind farm, 25 percent will go to the host municipality, and the remaining 1 percent to a citizens’ cooperative. Also involved in the municipal participation process is Regionalwerk Westliche Wälder, an association of eight municipalities from the districts of Augsburg and Dillingen an der Donau—the latter of which includes Holzheim.
The turbines will have a hub height of 175 meters and a total capacity of 28 MW. The projected electricity output of 55 million kWh is estimated to be sufficient to power approximately 22,000 households. Stadtwerke München has been involved in the development of the wind farms from an early stage and is overseeing construction on-site. Project managers expect to be able to deliver and install the major components—including rotor blades and nacelles—beginning in the fall of 2027.
Author: Volker Stephan