More Electricity for Bavaria's Chemical Triangle

The spatial impact assessment identifies several suitable route corridors and advances the expansion of the extra-high-voltage infrastructure for one of Bavaria's most important industrial locations.

November 19, 2026

Source: E & M powernews

The government of Upper Bavaria has assessed seven out of ten route corridors for the 380-kV “ChemDelta” transmission line as compatible with land-use planning. Two continuous route options are possible.

Tennet’s planned 380-kV Chem Delta power line is moving forward: Seven out of ten route corridors reviewed have been deemed compatible with land-use planning. This results in two possible continuous route options, allowing for a swift final selection of the route. This is evident from the regional planning assessment by the government of Upper Bavaria, which announced the results of the spatial compatibility assessment.

The assessment determined which route alignments and substation locations are compatible with regional planning requirements. In coordination with the government of Lower Bavaria, the government of Upper Bavaria examined ten route corridors and six potential sites between Burghausen and Simbach. The assessment focused primarily on the impacts on local residents, nature and the landscape, existing settlements, and the energy supply.

Two New Substations

For the two planned substations near Burghausen and Simbach, two locations each remain fundamentally suitable. A location near Haiming was deemed incompatible with land-use planning. In addition, the authority established requirements that must be taken into account during the specific design phase.

Bavaria’s State Secretary for Economic Affairs, Tobias Gotthardt, described the transmission line as crucial for ensuring a reliable supply of electricity to the Bavarian chemical triangle in the future. He noted that the assessment identified potential conflicts early on and provides greater planning certainty for Tennet.

The government of Upper Bavaria conducted the spatial compatibility assessment in about six months. It does not yet constitute approval: In the subsequent approval process, the specific route alignments and locations will be further developed and reviewed.

The “Chemical Triangle” spans the southeastern Bavarian districts of Altötting, Mühldorf, and Traunstein. The most important production sites are Burghausen (Wacker Chemie, OMV refinery), Trostberg (Alzchem, BASF), Waldkraiburg, and Burgkirchen (Gendorf Chemical Park). The new transmission line, with two 380-kV circuits, can supply approximately 5 MW to the Chemical Triangle and significantly improve the power supply to these sites.

Author: Günter Drewnitzky