High-altitude wind tower in Lusatia generates electricity

The first facility in Schipkau is intended to demonstrate the concept's practical feasibility and pave the way for additional high-altitude wind towers as well as future mass production.

November 23, 2026

Source: E & M powernews

Gicon has connected the world’s tallest high-altitude wind tower to the grid in Schipkau (Brandenburg). The 365-meter-tall wind turbine serves as a model for five additional planned towers.

The world’s tallest high-altitude wind tower (HWT) is now operational. The turbine, built by the Dresden-based company Gicon, has been connected to the power grid in Schipkau, in southern Brandenburg, and is now generating electricity. With a hub height of 300 meters and a total height of 365 meters, it reaches a height designed to capture more wind than conventional turbines on the same land area. The company plans to build five more turbines and aims to begin mass production by 2030 at the latest.

The commissioning on November 19 marks the completion of the first project phase for Gicon. “What stands before us today began with an idea that many initially considered almost unimaginable. The fact that the HWT is now connected to the grid and producing electricity fills me with great pride and gratitude,” said Prof. Jochen Großmann, founder and CEO of the company.

The high-altitude wind turbine project was developed in collaboration with the Federal Agency for Breakthrough Innovations (SPRIND). Gicon developed the high-altitude wind turbine concept and constructed the facility on behalf of Beventum GmbH, a subsidiary of SPRIND. According to the company, the 3.8-MW facility cost approximately 25 million euros. It reached its final height at the end of September 2026.

The technical design is based on a lattice tower and a steel structure consisting of approximately 22,000 individual parts. The hub height of 300 meters is designed to access wind currents that conventional wind turbines cannot reach. As a result, the tower is expected to achieve twice the energy yield of a conventional wind turbine. Insights gained from the construction and operation of the first turbine are being incorporated into the further development of the technology.

Yields comparable to offshore wind farms

In addition to the five high-altitude wind towers already planned, Großmann reports that letters of intent have been signed for the construction of 100 turbines in Germany. The company sees a potential application in the repowering of existing wind farms. It estimates that up to 4,000 high-altitude wind towers could be built there alone.

As it moves forward with development, Gicon plans to collaborate with local small and medium-sized enterprises. The experience gained from the first project is expected to help improve construction methods and reduce costs. The company plans to begin mass production by 2030 at the latest. It expects electricity yields on the same scale as those seen in offshore wind farms. Großmann therefore describes the concept as “offshore on land.”

In the long term, the levelized cost of electricity is expected to fall below the current level of conventional onshore wind energy. According to the company’s assessment, this will depend in particular on falling construction costs resulting from mass production. Whether the expected yields and cost advantages are confirmed in long-term operation will be determined by upcoming operational and project experience. The facility in Schipkau serves as the first reference project for this purpose.

Author: Susanne Harmsen